Water Filling Machine FAT Checklist and Acceptance Guide

The signed technical agreement should define the final FAT items, test materials, duration, measurement method and acceptance conditions.

01

Before the test

Confirm that the machine and test basis match the approved order.

  • Configuration and nameplate
  • Reference bottle and cap quantities
  • Utilities and product-water test condition
  • Approved FAT protocol
02

Run and observe

A water test should show more than motion.

  • Dry run and safety check
  • Continuous water run
  • Actual bottle count and rejects
  • Fill level, leakage and cap result
03

Test operating events

Observe controlled response outside steady-state operation.

  • Starvation and restart
  • Missing bottle or cap
  • Jam and alarm behavior
  • Changeover where included
04

Close the evidence package

Record open points before packing.

  • Spare-parts verification
  • Manual and drawing check
  • Photo or video records as agreed
  • Packing and shipment preparation
0 items selected

Final FAT items and acceptance conditions are confirmed in the signed technical agreement.